Contractor's irreducible guarantee period for solidity and safety is five years

AnswerThe contractor providing materials and execution is liable for the solidity and safety of substantial buildings for an irreducible period of 5 years due to materials and soil.

Reviewed on 2026-10-02 · next review 2027-04-02

Data

WhoCriterionConsequenceSourceData date
Contractor of materials and executionContracts for substantial buildings or other constructionsLiable for work's solidity and safety for an irreducible five-year period regarding materials and soilLaw 10.406/2002, art. 618, caput10/01/2002
Building ownerLapse of the right assured in art. 618The owner loses the right if no action is filed within 180 days after the defect appearsLaw 10.406/2002, art. 618, sole paragraph10/01/2002

Data consulted on 02/10/2026.

Basis

How it applies

The rule applies to construction contracts for substantial buildings or other structures where the contractor supplies materials and execution. The contractor is mandatorily responsible for the work's solidity and safety for 5 years, considering materials and soil. To exercise this right, the owner must file the action within 180 days counted from the appearance of the defect.